Road development process
[edit] Road improvement scheme: phases of development
A general example of a road improvement scheme would involve several steps, with the main phases in the development process being:
Followed by:
The design phase may be sub-divided in to two or three sub-phases:
[edit] Identifying the problem and possible solutions
As a first step, a highway authority would usually identify a safety or capacity related problem on its road network and investigate potential solutions. A well-functioning road should provide safe and reliable journeys, and contribute to the growth of a successful economy.
In highlighting a successful objective for undertaking a road improvement scheme, and using the strategic road network (SRN) as an example, the SRN must facilitate the efficient movement of people and goods.
For the SRN, if investigations highlight that there is a safety or capacity related problem, the Department for Transport (DfT) Circular 02/2013 explains that development proposals are likely to be acceptable if:
- They can be accommodated within the existing capacity of a section (link or junction) of the strategic road network; or
- They do not increase demand for use of a section that is already operating at over-capacity levels.
[edit] Concept / feasibility studies and consultation
If, after investigation, a viable road scheme is identified, a concept design and feasibility study would be carried out to identify the options.
The Highways Agency (now Highways England) published the Project Control Framework handbook (2013), which sets out how to manage and deliver major improvement projects.
In preparing a concept design for a major development, the highway engineer would address the practicalities of cost effective access for all modes of travel, assessment of the suitability of the existing infrastructure, the parking and servicing arrangements and the detailed design of on and off-site civil engineering works.
Feasibility studies involve both a desktop and a site visit, address the key fundamentals of access and access constraints. Investigations will also take place as to the current lawful use of the site and its present potential for generating traffic.
Upon completion, stakeholders and the public are consulted to help identify the preferred solution of the options identified.
[edit] Design and estimated costs
After choosing the preferred scheme, a preliminary design and estimate would be prepared. This is often carried out by a consultant who independently prepares the preliminary design to enable a decision to be taken on where the road should be located within the preferred route envelope. This design will include topographical, environmental and geographical surveys.
Once the design has been undertaken and an estimate prepared, the next step would be to prepare the Highways Act 1980 draft orders, and to publish and seek objections for the road improvement scheme.
[edit] Planning and legislation
Road improvement schemes must comply with the planning procedures that apply in the country in which they are located. For the Strategic Road Network, Highways England has produced a guide to working with them on planning matters - Planning for the Future (2015).
The guidance document describes the approach Highways England take to engaging in the planning system and the issues they look at when considering draft planning documents and planning applications. It offers advice on the information they would like to see included in a planning proposal, and outlines the support they can offer.
It is a useful aide for local authorities, developers, Local Enterprise Partnerships (LEPs), community groups and others involved in plan-making, development management, development promotion or decision-taking in respect of land close to any part of the Strategic Road Network (SRN).
[edit] Planning Act 2008 procedures
If the cost of the scheme is above the current threshold of £200 million for a Nationally Significant Infrastructure Project (NSIG), its implementation will come under the provision of the Planning Act 2008. For further information on the National Infrastructure Planning process, visit the National Infrastructure Planning website, which includes information and resources on this process, and advice on legislation.
[edit] Highways Act 1980
If the cost of the road improvement scheme is below the current £200 million threshold, a Planning Act 2008 draft development order is not needed, and you should refer to the Highways Act 1980. An Environmental Impact Assessment will be required for all road schemes. For Special Roads, the official classification of motorways, a draft order may need to be published and you should refer to the Highways Act 1980.
[edit] Public inquiry
A public inquiry is a formal procedure, usually reserved for significant major developments or proposals of a sensitive nature where all aspects of the development may need to be examined in detail.
Best practice for inquiries into local highway schemes is available from the Planning Inspectorate. A guide to public enquiries is also available from the Office of the Traffic Commissioner.
[edit] Report on procedures and decision on whether to proceed
Once these procedures have been followed and fully considered, a decision would then be taken on whether to proceed. Local authorities can agree to grant themselves planning permission for local roads. If the scheme is an NSIG however, the Secretary of State can call for a process of public inquiry.
[edit] Detailed design and preparation of contract documents
Once a road scheme receives planning permission, engineers can undertake the detailed design and preparation of contract documents.
Within the more detailed design, engineers should:
- Produce further detailed topographical, geological and geotechnical surveys.
- Produce detailed design of bridges/structures, drainage, earthworks and pavement.
- Consider health and safety and factor this into the detailed design.
[edit] Tendering process and construction period
Engineers should refer to the Highways England procurement strategy. This is an evolving document and is updated regularly.
Once the tender is awarded, construction is then in the hands of the successful contractor for the construction of the scheme to time.
[edit] Hand over to client, road opens and maintenance period begins
Once the construction phase is complete, the road is then handed over to the client authority for use by traffic. The contract then enters the maintenance period, where the contractor remains responsible for the road structure.
As a result of the final inspection prior to handover, there are usually minor problems identified, which the contractor must correct, or pay to correct. The work undertaken by the contractor during the maintenance period is separate from normal road maintenance activities.
[edit] Useful resources
Highways England produces standards and documentation relating to the design, construction and maintenance of highways. Documents are available free online, including:
The Design Manual for Roads and Bridges (DMRB) contains information about current standards, advice notes and other published documents relating to the design, assessment and operation of trunk roads, including motorways. The DMRB has been prepared for trunk roads and motorways.
The Manual of Contract Documents for Highway Works contains the primary documents required for the preparation of contracts for trunk road works. It consists of several parts, including the administrative procedures for its use, the specification for highway works and the corresponding method measurements.
Interim Advice Notes (IANs) issued by Highways England contain specific guidance, which should only be used in connection with works on motorways and trunk roads in England, subject to any specific implementation instructions contained within an IAN. IANs are not part of the DMRB and the MCHW but must be read in conjunction. They may incorporate amendments or additions to documents in these manuals.
Eurocodes - As a public body, Highways England expresses its requirements for the design and modification of existing structures (including geotechnical works) in terms of Eurocodes. Highways England’s technical experts were involved in the drafting of the Eurocodes and the National Annexes.
The Network Management Manual (NMM) provides mandatory requirements, guidance and advice for the management of maintenance of the trunk road network.
The performance requirements for routine and winter service activities on the trunk road network are included in the Routine and Winter Service Code.
The Traffic Management and Maintenance Manual, published in January 2013, sets out requirements for the management and maintenance of traffic technology systems.
Further information related to standards for highways is also available on the Standards for Highways online resource webpage.
This article originally appeared as The road development process: An overview, published by the Institution of Civil Engineers on 30 March 2016. It was written by Adam Kirkup.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings
- Articles by ICE on Designing Buildings Wiki.
- Car park.
- Code of Practice for Ironwork Systems Installation and Refurbishment.
- Conserving and Enhancing Country Lanes in the Surrey Hills AONB.
- Consultation process.
- Design and Check Certificates.
- DurabRoads.
- Groundwater control in urban areas.
- Highway authority.
- Highway drainage.
- Highways England.
- Infrastructure.
- Kerbs.
- Mobile asphalt stations.
- NEC contracts - road development and management schemes.
- Pavement.
- Platooning.
- Road construction.
- Road improvement scheme consultation.
- Road joints.
- Road traffic management.
- The history of the dimensions and design of roads, streets and carriageways.
- Technical consultation on planning.
- Types of road and street.
- Successful road kerb trial.
Featured articles and news
About the 5 Percent Club and its members
The 5% Club; a dynamic movement of employers committed to building and developing the workforce.
New Homes in New Ways at the Building Centre
Accelerating the supply of new homes with MMC.
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.